HomeMy WebLinkAbout32348 XXX 115 08-10-2022 SWMR 4C-008EV7W40 MCM INSPECTION REPORT ENVIRONMENTAL LANDFILL INC Environmental Landfill Inc : KQRW-TKQE-P5Z
Site Investigation Memo
Inspector: Craig Mangham
Start Date: 08/10/2022 Completed Date: 08/15/2022
Inspection Information
1. Site Investigation Date 08/10/2022
2. Inspector Craig Mangham
3.ADEM Complaint Number 4C-008EV7W40
4. Site Name Environmental Landfill
Inc
5. Physical Address
1317 Annie Lee Road,Trussville,AL 35173
6. Nearest City Trussville
7. County St Clair
8a. Site Coordinates Latitude 33.6187340
8b. Site Coordinates Longitude -86.529356
9. Paroel Number 2508270001
003000, 25 05 22 0
001 014000, 25 05 22
0001 013002, 25 05 22
0001 013001, 25 05 22
0001 013000
10. Inspection Type Follow Up
11. Site Referred No
Contact Information 1
Contact Role Responsible Party
1. Name Environmental Landfill
Inc
2.Title
3. Mailing Address 1 1317 Annie Lee Road
4. Mailing Address 2
S. City Trussville
6. State AL
7. Zip Code 35173
8. Phone Number
8/15/2022 8:17 AM 1
Environmental Landfill Inc : KQRW-TKQE-P5Z
Site Investigation Memo
Inspector: Craig Mangham
Start Date: 08/10/2022 Completed Date: 08/15/2022
Contact Information 1
9. Email
On-Site C
On-Site Contacts
Name tie Phone Email Comments
Charlie and Aimee Operators
Rich
ite Investigation Details
1. Innocent Landowner No
2. Property Type Commercial
3. Waste Description / Composition Construction
Demolition Waste
4. Estimated Volume of Regulated Solid Waste 99999
Observation 8/10/2022
Determined:
10710: Removal & Response -Waste
Volume - Unauthorized Dump
At the time of inspection, the amount of Construction demolition waste could not be determined on
-site. Previous inspections indicated that construction demolition waste had been buried on-site.
photo Taken: 8/10/202211:28:57 AM
a
Area where creosote-coated power poles and
pallets were previously located. Facility personnel
indicated that they had been taken to appropriate
landfills.
8/15/2022 8:17 AM 2
Environmental Landfill Inc : KQRW-TKQE-P5Z
Site Investigation Memo
Inspector: Craig Mangham
Start Date: 08/10/2022 Completed Date: 08/15/2022
Site Investi ation Details
FF Photo Taken: 8/10/2022 11:30:50 AM
* .. Area of the previously identified"hotspots"of
buried construction demolition waste.
Photo Taken: 8/10/2022 11:32:41 AM
Area of the previously identified"hotspots"of
buried construction demolition waste. Tree waste
visible.
Photo Taken: 8/10/2022 11:32:54 AM
Area of the previously identified"hotspots"of
buried construction demolition waste. Plywood
visible on top of the pile of tree waste.
8/15/2022 8:17 AM 3
Environmental Landfill Inc : KQRW-TKQE-P5Z
Site Investigation Memo
Inspector: Craig Mangham
Start Date: 08/10/2022 Completed Date: 08/15/2022
Site Investigation Details
Photo Taken: 8/10/2022 11:33:10 AM
Area of the previously identified'Totspots"of
buried construction demolition waste.
Photo Taken: 8/10/2022 11:33:38 AM
Area of the previously identified'Totspots"of
buried construction demolition waste. Tree waste
visible.
Photo Taken: 8/10/2022 11:33:55 AM
Area of the previously identified'Totspots"of
buried construction demolition waste.
8/15/2022 8:17 AM 4
Environmental Landfill Inc : KQRW-TKQE-P5Z
Site Investigation Memo
Inspector: Craig Mangham
Start Date: 08/10/2022 Completed Date: 08/15/2022
Site Investigation Details
Photo Taken: 8/10/2022 11:35:02 AM
Area of the previously identified"hotspots"of
buried construction demolition waste. Tree waste
visible.
r
Photo Taken: 8/10/202211:35:58 AM
Area of the previously identified"hotspots"of
buried construction demolition waste. Tree waste
visible.
4 .
Y
Photo Taken: 8/10/2022 11:42:48 AM
Overview of the previously identified"hotspots"of
_ _ Y buried construction demolition waste. Tree waste
visible on the slopes.
4a. Regulated Solid Waste Unit
8/15/2022 8:17 AM 5
Environmental Landfill Inc : KQRW-TKQE-P5Z
Site Investigation Memo
Inspector: Craig Mangham
Start Date: 08/10/2022 Completed Date: 08/15/2022
Site Investigation Details
5. Number of Scrap Tires 0
6. Inspector Comments
Inspection conducted as a follow up to the 12/2/2020 follow up inspection in which an unknown
amount of construction demolition waste was identified on-site. At the time of the 8/10/2022
inspection, tree waste was primarily observed on-site, with very little construction demolition waste
observed in piles on top of tree waste. At the time of the 8/10/2022 follow up inspection,the
previously observed creosote coated power poles and pallets had been removed from the site and
taken to the appropriate landfills. At the time of inspection, Mr. Rich indicated that he plans to
have the site completely remediated in 18 months, working approximately 6 months at a time in
the three previously identified "hotspots"of buried construction demolition waste.
Ranking Criteria
1. Site Proximity To The Following: (Within View Of Site) Churches, Other
Populated Structures,
Utilities, Roadways,
Railroads, Etc.
2. Known Presence Of Human/Animal Infections Or Diseases? No
3. Fire Hazard (Lack Of Availability Of Adequate Water, Yes
Location/Composition Of Tim Piles)?
4. Suspected Presence Of Special Waste (ADEM Admin. Code R. 335-13-4 No
-.26)?
5. Environmental Justice Area? No
6. Adverse Impacts To Surface Water? No
7. U.S. Army Corps Of Engineers Wetland Referral? No
8/15/2022 8:17 AM 6